Benton Harbor - Fair PlainTransmission Line Rebuild Project


Indiana Michigan Power representatives plan to upgrade the electric transmission network serving customers in the cities of Benton Harbor and Fair Plain in southwestern Michigan. The project involves:

  • Updating approximately 7 miles of 34.5 kV transmission line to 69 kV standards

The project increases electric reliability in the area by updating the local transmission infrastructure to modern standards. Company representatives plan to rebuild some sections of the power line in the existing right-of-way, which could require updating or supplementing current easements. Other sections of the project include re-routes that require new easements.

Project Updates

Early 2024: Since the final line route was selected in summer 2021, I&M representatives have been performing field activities to support the engineering and design of the line. As the project has progressed, we found the need to adjust the originally proposed timeline. Company officials now expect construction to begin spring 2025 and conclude later that summer.

Timeline

Project Timeline

Structures

Structure

The project involves installing steel poles.

Structure Height: Approximately 75 feet*
Right-of-Way Width: Approximately 60 feet*

* Exact structure, height and right-of-way may vary

Resources

Project Fact Sheet Project Map Access Roads Field Activities

Indiana Michigan Power serves 575,000 customers in Indiana and Michigan.

www.IndianaMichiganPower.com

Eric Giffey

Project Outreach Specialist
614-736-8971